Strawman plan workshop
Put up a deliberately rough plan for the whole discovery and let the team knock it down, so they commit to a shape.

- Time
- 1–1.5 hours
- People
- Core team leads, sponsor optional
Overview
A working session that puts up a deliberately incomplete plan for the whole discovery — the strawman — and invites the team to knock it down. It sits at the discovery kick off: the strawman is what you bring into that meeting, to get an initial reaction and set managed expectations for what activities are potentially part of the discovery. This also communicates who is involved in which activity, matching their capacity and expected engagement through the discovery.
The strawman itself comes from the Proposed approach section of the Discovery Introduction, which lays out five activities per pillar. You are not inventing a plan from nothing; you are adapting a known one and finding out where it does not fit this project.
When to use it.
Right at the start of pre-framing, before scoping the discovery in detail. Particularly worth it when the sponsor has a delivery date in mind and the team has not yet said out loud what will fit inside it.
Who to involve.
The leads of the core team — keep this small. The sponsor’s presence is optional: the Discovery Lead can bring the resulting plan to them afterwards as a proposal, rather than building it together in the room.
Effort.
High prep Medium engagement One facilitator, whose preparation is adapting the deck’s activities to this project beforehand rather than starting from a blank board.
Outcomes.
An agreed list of discovery activities and the order they run in, with the ones that do not apply here explicitly dropped. Not dates — those come after framing has told you how much there is to learn.
Recommendations.
Say “strawman” out loud, repeatedly: people will not attack a plan they think is already agreed. Do not defend it — your job is to have written something down, not to be right about it. A plan nobody has objected to is a plan nobody has read.
How to run it
Send a proposal of the strawman plan as a pre-read before the session: the deck’s five activities per pillar, adapted to this project.
Place the activities on the board
On a whiteboard or working board, lay out the activities from the pre-read, one phase at a time.
Invite the team to break it
Which of these does not apply here? What is missing? Where is the sequence wrong for this project? Use this pass to also identify the participants to include for each activity.
Commit to a shape, not a schedule
Leave with the activities the team agrees to and the order they go in.